Question
File Edit View History Bookmarks People Window Help Take a Test- walhan youhanan Secure https://www.mathal.com/Student/PlayerTest.aspx?testid 184040988&cern; erwinayes walhan youhanan | 6/29/18 Time Remaining: 00-3036 S This Quiz: 10 p BUS 121-Section 1838-ONLINE Summer 2018 Quiz: Ch 4 Quiz This Question: 1 pt 3 of 10 (5 complete) Beaver Company manufactures coffee tables and uses an activity-based costing system to allocate all manufacturing conversion costs. 30 separate Activity Materials handing Number of parts parts totaling $190 in direct materials, and requires 4 hours of machine d time to produce. Additional information folows Cost Allocation Rate 1.00 per part $5.40 per machine hour $4.00 per part Allocation Base Machine hours Number of parts Number of finished units $5.00 per finished unt What is the total manufacturing cost per coffee table? O A $176.60 O B. $162.00 C. $366.60 OD. S361.60 Click to select your answer 29 20 FS F6 F7 FS 1OExplanation / Answer
Answer is C ($ 366.6)
Calculation in details is as under:
ACTIVITY ALLOCATION BASE COST ALLOCATION RATE $ TOTAL
COST
MATERIAL COST 190` 190
MATERIALS
HANDLING NO.OF PARTS $1.0 PER PART 30X1 30
MACHINING MACHINE HOURS $ 5.4 PER MACHINE HOUR 4X5.4 21.6
ASSEMBLING NO. OF PARTS $ 4 PER PART 30X4 120
PACKAGING NO.OF FINISHED UNITS $5 PER FINISHED UNITS 1X5 5
------
366.6
_____
Related Questions