On February 1, 2018, Arrow Construction Company entered Into a three-year constr
ID: 2392601 • Letter: O
Question
On February 1, 2018, Arrow Construction Company entered Into a three-year construction contract to build a bridge for a price of $8,540,000. During 2018, costs of $2180,000 were Incurred with estimated costs of $4,180,000 yet to be Incurred. Billings of $2,680,000 were sent, and cash collected was $2,430,000 In 2019, costs Incurred were $2,680,000 wIth remaining costs estimated to be $3,870,000. 2019 billings were $2,930,000 and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of $3,980,000 were Incurred. The company's fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion. Required 1. Compute the amount of revenue and gross profit or loss to be recognized In 2018, 2019, and 2020 using the percentage of completion method? 2a. Prepare Journal entries for 2018 to record the transactions described (credit "various accounts" for construction costs Incurred). 2b. Prepare Journal entries for 2019 to record the transactions described (credit "varlous accounts" for construction costs Incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019. Complete this question by entering your answers in the tabs below Req 1 Req 2A Req 2B Req 3A Req 3B Compute the amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020 using the percentage of completion method? (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Round your final answers to the nearest whole dollar.) Percentages of completion Choose numerator | | Choose denominator | | % complete to date 2018 2019 100.0000% 2018 To date Recognized in prior years Re Recognized in 2018 Construction revenue Construction expense Gross profit (loss) 2019 To date Recognized in prior years Re Recognized in 2019 Construction revenue Construction expense Gross profit (loss) 2020 To date Recognized in prior years Re cognized in 2020 Construction revenue Construction expense Gross profit (loss)Explanation / Answer
2927233
(8,540,000 * 34.2767 %)
4754227
(8,540,000 * 55.6701%)
Percentages of completion Choose numerator ÷ Choose denominator = % complete to date 2018 2180000 ÷ 6360000 = 34.2767 % 2019 4860000 ÷ 8730000 = 55.6701 % 2020 100%Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.