Pick the correct answer, show work 30. Lewis Company calculates its predetermine
ID: 2388595 • Letter: P
Question
Pick the correct answer, show work
30. Lewis Company calculates its predetermined rates using practical volume, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Overhead is applied using direct labor hours. The total budgeted overhead is $3,168,000, of which $864,000 is fixed overhead. The actual results for the year are as follows:
Units produced: 280,000
Direct labor: 570,000 hours @ $9
Variable overhead: $2,320,000
Fixed overhead: $872,000
The predetermined fixed overhead rate is:
a. $3 per direct labor hour.
b. $1.50 per direct labor hour.
c. $5.50 per direct labor hour.
d. $4 per direct labor hour.
e. none of these.
31. The predetermined variable overhead rate is:
a. $3.00 per direct labor hour.
b. $1.50 per direct labor hour.
c. $5.50 per direct labor hour.
d. $4.00 per direct labor hour.
e. none of these.
32. Calculate the applied fixed overhead.
a. $840,000
b. $855,000
c. $864,000
d. $910,000
e. none of these
33. Calculate the fixed overhead spending variance.
a. $32,000 F
b. $0
c. $8,000 U
d. $32,000 U
e. $8,000 F
Explanation / Answer
30.Option " b" is the correct answer pre determined over head rate = Expected over head / allocation base = $864000 / 576000 hours = 1.50 [here labor hours = 288000 *2 = 576000 hours ] 31.option " d" is the correct answer. = [$3168000-$864000]/576000 = $4 32.option "C" is the correct answer here first the budgeted fixed over head would be applied , and then the mangement will decide wether it is under applied or over applied.The under /over applied cost wiil be adjusted with cost of good sold a/c. 33.option "c" is the correct answer. $864000-$872000 = $ 8000 un favourableRelated Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.