Munoz Corporation uses activity-based costing to determine product costs for ext
ID: 2387895 • Letter: M
Question
Munoz Corporation uses activity-based costing to determine product costs for external financial reports. At the beginning of the year, management made the following estimates of cost and activity in the company's five activity cost pools:
Activity cost pool Activitymeasure EstimatedOH Cost Expected Activity
Labor related Direct labor hours 210000 35,000 DLHs
Purchase orders Number or orders 72000 900 orders
Product testing Number of test 168000 1,400 tests
Template Etching Number of templates 315000 10,500 templates
General factory Machine hours 840000 70,000 MHS
Required:
1) Compute the activity rate (i.e predetermined overhead rate) for each of the activity cost pools.
2) During the year, actual overhead cost and acyivity were recorded as follows
Requirement 2: During the year, actual overhead cost and activity were recorded as follows: Activity Cost Pool Actual Overhead Cost Actual Activity Labor related $ 205,000 32,000 DLHs Purchase orders 74,000 950 orders Product testing 160,000 1,300 tests Template etching 338,000 11,500 relays General factory 825,000 68,000 MHs Total manufacturing overhead cost $ 1,602,000 a. Prepare a journal entry to record the incurrence of actual manufacturing overhead cost for the year (credit Accounts Payable). Post the entry to the company's Manufacturing Overhead T-account. (Record the transactions in the given order. Omit the "$" sign in your response.)
Explanation / Answer
2. Actual overhead cost Actual Activity labor related $205.000 32,000 DLHs $6.04 Purchase orders 74,000 950 0ders 77.89 Product testing 16,000 1,300test 12.30 Templating etching 338,000 11,500 29.39 General factory 825,000 68,000 68.00 Activity cost pool Estimated OH cost/ Expected Activity Activity based overhead Rate Labor relaed Directlabor hours .21,000/ $35,000 $0.6 per labor hour Puchase orders Number or orders 72,000/ 900 80 Product testing Number of test 168,000 1,400 tests $120 Template Etching Number of templatesmpls 315,000 10,500templates $30 General factory machine hours 840,000 70,000MHS 12Related Questions