Green Construction Co. has consistently used the percentage-of-completion method
ID: 2387103 • Letter: G
Question
Green Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2010, Green entered into a fixed-price contract to construct an office building for $12,000,000. Information relating to the contract is as follows: 2010 2011percentage of compeltion 15% 45%
estimated total cost at completion 9,000,000 9,600,000
gross profit recognized (cumulative) 600,000 1,440,000
Contract costs incurred during 2011 were
(a) 2,970,000
(b) 3,150,000
(c) 4,320,000
(d) 2,880,000
Explanation / Answer
(b) 3,150,000