Question

An employee of Morgan Corporation has found some partially completed units of Model X in a dusty corner of the warehouse. A job ticket attached to the units indicates that a total of $750 in manufacturing costs have been used to bring the materials to this point in the manufacturing process. The units can be sold in their current condition for $200 to a scrap metal dealer. If Morgan spends $250 to complete the units, they could be sold for $600.

Required: A. What should Morgan do? Why?
B. Identify the sunk cost, if any.

Explanation / Answer

A. Morgan Company should complete the units for $250 because if they sell them for $600, they will make a profit of $350, which is greater than the $200 they would get for selling the units. B. The sunk cost is the $750 in manufacturing costs. This cost has already been incurred and will remain incurred regardless of if Morgan Co sell or finishes the units.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote