Wilson Co. purchased land as a factory site for $800,000. Wilson paid $80,000 to tear down two buildings on the land. Salvage was sold for $5,400. Legal fees of $3,480 were paid for title investigation and making the purchase. Architect's fees were $31,200. Title insurance cost $2,400, and liability insurance during construction cost $2,600. Excavation cost $10,440. The contractor was paid $2,500,000. An assessment made by the city for pavement was $6,400. Interest costs during construction were $170,000.The cost of the building that should be recorded by Wilson Co. is
a. $2,503,800
b. $2,504,840
c $2,513,200
d. $2,514,240
Explanation / Answer
Wilson Co. purchased land as a factory site for
Cost $600,000
Tear down $60,000
Salvage ($5,400)
Legal fees $3,480
Title insurance $2,400
pavement $6,400
Total $666,880
The cost of the land that should be recorded by Wilson Co. is
b. $666,880.
Please rate the answer
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.