The The levels of production and of manufacturing overhead for the first five months of 2009 for Apex Products are shown below.
UN Units Produced Mfg. Overhead
JJ January 11,500 $58,650
Fs February 12,250 $59,413
March 11,125 $58,262
A April 11,950 $59,104
May 10,750 $57,889
a. Using the high-low method, compute the variable element of manufacturing overhead per unit of production.
Please show ALL WORK for answers.
Fe
Explanation / Answer
a. Using the high-low method, compute the variable element of manufacturing overhead per unit of production.
Variable cost per unit = (59413-57889)/(12250-10750) = 1.016
b. Using the high-low method, compute monthly overhead cost.
Monthly overhead cost = 59413- 12250*1.016 = $46967
c. Using the high-low method, compute the total estimated manufacturing overhead for June.
Total Estimated manufacturing overhead for june = 46967+ (1.016 * Expected unit to be produce)