The following data is given for the Harry Company:
Determine the direct labor time variance.
Select the correct answer.
Budgeted production 1,063 units Actual production 963 units Materials: Standard price per ounce $1.89 Standard ounces per completed unit 11 Actual ounces purchased and used in production 10,275 Actual price paid for materials $21,064 Labor: Standard hourly labor rate $15.00 per hour Standard hours allowed per completed unit 5.0 Actual labor hours worked 4,959 Actual total labor costs $75,625 Overhead: Actual and budgeted fixed overhead $1,155,028 Standard variable overhead rate $25.00 per standard labor hour Actual variable overhead costs $138,852 Overhead is applied on standard labor hours.Explanation / Answer
c. $2,160 U
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.