The following data relate to direct materials costs for November: Actual costs 4
ID: 2370719 • Letter: T
Question
The following data relate to direct materials costs for November: Actual costs 4,500 pounds at $6.00 Standard costs 4,600 pounds at $5.50 What is the direct materials price variance?<?xml:namespace prefix = o ns = "urn:schemas-microsoft-com:office:office" /> <?xml:namespace prefix = v ns = "urn:schemas-microsoft-com:vml" /> <?xml:namespace prefix = w ns = "urn:schemas-microsoft-com:office:word" /> a. $2,250 favorable b. $2,250 unfavorable c. $2,300 unfavorable d. $1,700 unfavorableExplanation / Answer
Hi,
Material Price Variance = Actual Qty *(AR - SR)
= 4500*(6 - 5,5) = 2300 (U)
Option C is correct.