Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Harriman Enterprises has three possible projects. Each project requires the same

ID: 2363834 • Letter: H

Question


Harriman Enterprises has three possible projects. Each project requires the same initial investment of $1,000,000. Harriman's chief financial officer has prepared the following cash flow projections for each project:

Jim Harriman, the company's president, is unsure of which project to pursue. Each holds promise for the company, but he is confused about what to do because each project generates the same amount of cash flow over the four-year period.


Ignoring taxes, compute the net present value of each project at a 15 percent cost of capital.








Project Net Present Value X: $ Y: $ Z: $

Explanation / Answer

DIsc rate 15% NPV of Proj X = NPV(Rate,CF1...CF4) + CF0 = NPV(15%,1250000,1250000,1250000,1250000,) - 1000000 = $2,568,723 NPV of Proj Y = NPV(15%,0,0,0,5000000) - 1000000 = $1,858,766 NPV of Proj Z = NPV(15%,500000,2000000,2000000,500000) - 1000000 = $2,547,979 Using excel PV function, Proj X: We have PV of CFs = Proj Y , PV of CF = 2,858,766.23 So NPV = 2,858,766.23 -1000000 = $1,858,766.23 Proj Z, PV of CF = 3,547,979.03 So NPV = 3,547,979.03 - 1000000 = 2,547,979.03 So Proj X with highest NPV should be selected.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote