Manner Corporation is trying to determine how long it takes for one product to p
ID: 2354794 • Letter: M
Question
Manner Corporation is trying to determine how long it takes for one product to pass through the production process. The following information was gathered regarding how many days the product spent in various production activities:..... Activity = Inspection...Number of days = 5... Activity = Storage ... Number of days = 6..... Activity = Assembly... Number of days = 3... Activity = Handling... Number of days = 2... Activity = Painting... Number of days = 3 ..... Activity = Packaging..... Number of days = 1 ...... a. Which of the above activities is value added?..... b. What is MannerExplanation / Answer
(a) Value added activity - Assembly, Painting, packaging Non-value added activity - Inspection, storage, handling (b) Total cycle time = 5 + 6 + 3 + 2 + 3 + 1 = 20 days (c) Total value added time = 3 + 3 + 1 = 7 days Manner’s manufacturing efficiency ratio = 7/20 x 100 = 35% (d) By implementing the system, storage and handling time can be eliminated. Total cycle time = 20 - 2 - 6 = 12 days This will result in the new manufacturing efficiency ratio be 7/12 x 10% = 58.3% Hope this helps!
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.