Support Departments Producing Departments Personnel Maintenance Fabrication Asse

ID: 2347672 • Letter: S

Question


 

Support

Departments

Producing

Departments

 

Personnel

Maintenance

Fabrication

Assembly

Budgeted overhead

$160,000 

$288,000  

$560,000  

$640,000

Direct labor hours

8,000 

10,000  

32,000  

40,000

Machine hours

12,000 

15,000  

48,000  

32,000

Number of employees

16 

20  

60  

100

 

Personnel costs are allocated based on the number of employees, and maintenance costs are allocated based on machine hours.

 

Predetermined overhead rates for fabrication and assembly are based on direct labor hours. (Round to the nearest dollar.) 

 

The amount of maintenance costs allocated to the Assembly Department using the direct method would be

a.

$115,200

b.

$192,000

c.

$57,600

d.

$152,640


 



Support


Departments



Producing


Departments



 



Personnel



Maintenance



Fabrication



Assembly



Budgeted overhead



$160,000 



$288,000  



$560,000  



$640,000



Direct labor hours



8,000 



10,000  



32,000  



40,000



Machine hours



12,000 



15,000  



48,000  



32,000



Number of employees



16 



20  



60  



100


Explanation / Answer



(Allocated Amount = 288000*(32000/(32000+48000))

The answer is A)115200