\"Blast it!\" said David Wilson, president of Teledex Company. \"We\'ve just los
ID: 2346688 • Letter: #
Question
"Blast it!" said David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers job by $9,900. It seems we're either too high to get the job or too low to make any money on half the jobs we bid."Teledex Company manufactures products to customers' specifications and operates a job- order costing system. Manufacturing overhead cost is applied to jobs on the basis of direct labor cost. The following estimates were made at the beginning of the year:
Fabricating Machining Assembly Total plant
Direct labor $300,000 $201,000 $400,000 $901,000
Manufacturing overhead $537,000 $806,010 $100,000 $1,443,010
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required manufacturing costs in the three departments as follows:
Fabricating Machining Assembly Total plant
Direct materials $11,900 $800 $5,500 $18,200
Direct labor $6,500 $1,700 $12,900 $21,100
Manufacturing overhead ? ? ? ?
At the end of the year, the company assembled the following actual cost data relating to all jobs worked on during the year:
Fabricating Machining Assembly Total Plant
Direct materials $761,000 $90,000 $410,000 $1,261,000
Direct labor $320,000 $210,000 $341,000 $871,000
Manufacturing overhead $561,000 $830,000 $93,000 $1,484,000
A) Compute the underapplied or overapplied overhead for the year, assuming that a plantwide overhead rate is used.
B) Compute the underapplied or overapplied overhead for the year, assuming that departmental overhead rates are used.
-fabricating
-machining
-assembly
-total plant
Explanation / Answer
Hi, Please find the calculations as below: Predetermined Overhead Rate based on direct labor cost: 1,443,010/901,000 = 1.60 Applied Overhead using this rate would be = 1.6 * 871000 = 1393600 Underapplied Overhead = 1,443,010 - 1,393,600 = 49410 Departmental Overhead Rates based on DL Cost Fabricating = 537000/300000 = 1.79 or 1.8 Machining = 806010/201000 = 4.01 or 4 Assembly = 100000/400000 = .25 Applied Overhead Fabricating = 1.79 or 1.8 = 1.79 * 320000 = 572800 Machining = 4.01 or 4 = 4.01 * 210000 = 842100 Assembly = .25 * 341000 = 85250 Plant = 572800 + 842100 + 85250 = 1500150 Underapplied or Overapplied Fabricating = Actual - Applied = 561000 - 572800 = 11800 (Over) Machining = Actual - Applied = 830000 - 842100 = 12100 (Over) Assembly = Actual - Applied = 93000 - 85250 = 7750 (Under) Plant = Actual - Applied = 1484000 -1500150 = 16150 (Over) Thanks, Aman Assembly = Actual - Applied = Plant = Actual - Applied =
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.