6. s (Product C and Product 2) using two different activities Machining, which uses machine hours as an . The cost of Machining is $945,000, while the cost of Inspection is Washington, Inc. produces two different products (Product C and Product 2) using two different actvities Machining activity driver, and Inspection, which uses number of batches as an activity driver $37.370 The activity drivers are used as follows Machine hours Number of batches Product C 1,900 53 Product 2 3,500 21 Total 5,400 74 What is the activity rate for Inspection? O $175 per batch O $505 per batch O $1780 per batch O $705 per batch Type here toExplanation / Answer
Activity cost driver rate
= Budgeted cost / Budgeted activity
Activity for Inspection is Number of batches that is 74 and cost for Inspection is $37,370
So, Activity cost driver rate
= $37,370 / 74
= $505 per batch
So, as per above calculations, option B is the correct option
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.