Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Exercise 4-7 Contrast ABC and Conventional Product Costs [LO4-2, LO4-3, LO4-4] K

ID: 2342050 • Letter: E

Question

Exercise 4-7 Contrast ABC and Conventional Product Costs [LO4-2, LO4-3, LO4-4]

Kunkel Company makes two products and uses a conventional costing system in which a single plantwide predetermined overhead rate is computed based on direct labor-hours. Data for the two products for the upcoming year follow:

Mercon

Wurcon

Direct materials cost per unit

$

9.00

$

7.00

Direct labor cost per unit

$

15.00

$

17.00

Direct labor-hours per unit

0.40

4.80

Number of units produced

4,000

8,000

These products are customized to some degree for specific customers.

Required:

1. The company's manufacturing overhead costs for the year are expected to be $1,600,000. Using the company's conventional costing system, compute the unit product costs for the two products.

2. Management is considering an activity-based costing system in which half of the overhead would continue to be allocated on the basis of direct labor-hours and half would be allocated on the basis of engineering design time. This time is expected to be distributed as follows during the upcoming year:

Mercon

Wurcon

Total

Engineering design time (in hours)

8,000

8,000

16,000

Compute the unit product costs for the two products using the proposed ABC system.

(For all requirements, do not round intermediate calculations. Round your final answers to 2 decimal places.)

Mercon

Wurcon

Direct materials cost per unit

$

9.00

$

7.00

Direct labor cost per unit

$

15.00

$

17.00

Direct labor-hours per unit

0.40

4.80

Number of units produced

4,000

8,000

Explanation / Answer

Using the company's conventional costing system

Mercon

Wurcon

Total

Direct labor-hours per unit

0.4

4.8

Number of units produced

4000

8000

Direct labor hours (multiply of above both)

1600

38400

40000

Manufacturing overhead costs

1600000

Total direct labor hours

40000

Overhead rate per labour hour

$    40.00

Mercon

Wurcon

Direct materials cost per unit

9

7

Direct labor cost per unit

15

17

Overhead per unit (Mercon = 40*0.4) (Wurcon =40*4.8)

16

192

Unit product costs

$    40.00

$ 216.00

Activity-based costing system

Half of the overhead would continue to be allocated on the basis of direct labor-hours and half would be allocated on the basis of engineering design time.

Cost

Cost driver

Total activity

Cost driver rate (cost / total activity)

Overhead

800000

Direct labor hour

40000

$    20.00

Engineering design cost

800000

Engineering design time

16000

$    50.00

1600000

Mercon

Wurcon

Overhead general (Mercon =20*1600) (Wurcon =20*38400)

32000

768000

Engineering design cost (Mercon =50*8000) (Wurcon =50*8000)

400000

400000

Total allocated overhead

432000

1168000

Number of units produced

4000

8000

Allocated overhead per unit

108

146

Mercon

Wurcon

Direct materials cost per unit

9

7

Direct labor cost per unit

15

17

Overhead per unit (Mercon = 40*0.4) (Wurcon =40*4.8)

108

146

Unit product costs

$ 132.00

$ 170.00

Using the company's conventional costing system

Mercon

Wurcon

Total

Direct labor-hours per unit

0.4

4.8

Number of units produced

4000

8000

Direct labor hours (multiply of above both)

1600

38400

40000

Manufacturing overhead costs

1600000

Total direct labor hours

40000

Overhead rate per labour hour

$    40.00

Mercon

Wurcon

Direct materials cost per unit

9

7

Direct labor cost per unit

15

17

Overhead per unit (Mercon = 40*0.4) (Wurcon =40*4.8)

16

192

Unit product costs

$    40.00

$ 216.00