Hibshman Corporation bases its predetermined overhead rate on the estimated mach
ID: 2336658 • Letter: H
Question
Hibshman Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. At the beginning of the most recently completed year, the Corporation estimated the machine-hours for the upcoming year at 10,000 machine-hours. The estimated variable manufacturing overhead was $6.82 per machine-hour and the estimated total fixed manufacturing overhead was $230,200. The predetermined overhead rate for the recently completed year was closest to: Multiple Choice $29.84 per machine-hour $23.15 per machine-hour $23.02 per machine-hour $6.82 per machine-hour
Explanation / Answer
The predetermined overhead rate = (Total Overhead ) / Total machine-hours
= ( estimated total fixed manufacturing overhead + estimated total Variable manufacturing overhead ) / Total machine-hours
= [ ($ 230,200 ) + ( $ 6.82 * 10,000) ] / 10,000
= $ 29.84 per machine hour
Hence the correct answer is $ 29.84 per machine-hour