Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

During 2017, Pina Company started a construction job with a contract price of $1

ID: 2331494 • Letter: D

Question

During 2017, Pina Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available.

2017

2018

2019

2017: $

2018:$

2019:$

During 2017, Pina Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available.

2017

2018

2019

Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 –0– Billings to date 301,000 897,000 1,610,000 Collections to date 271,000 817,000 1,428,000

Explanation / Answer

Answers

1) No profit or loss will be recorded in the year 2017 and 2018 under Compete Contract Method .

2) The Profits or loss under both methods will be Exactly same, The only difference is Profit or loss is recognised in year of completion in case of Completed Contract method and under Percentage on completion method Profit or loss is recognised in all years in which work is done.

Working

Year end 2017

Year end 2018

Year end 2019

A

Contract Price

$       1,610,000.00

$ 1,610,000.00

$ 1,610,000.00

B

Cost Incurred to Date

$           434,300.00

$      859,560.00

$ 1,073,000.00

C

Estimated cost yet to be incurred to complete the contract

$           575,700.00

$      242,440.00

$                        -  

D = B+C

Total Cost

$       1,010,000.00

$ 1,102,000.00

$ 1,073,000.00

E = (D/B) x 100

% of Completion

43.00%

78.00%

100.00%

F = A x E

Revenue to date

$           692,300.00

$ 1,255,800.00

$ 1,610,000.00

G

Revenue of Previous year

$                            -  

$      692,300.00

$ 1,255,800.00

H = F - G

Net Revenue this year

$           692,300.00

$      563,500.00

$      354,200.00

I (=B)

Cost to date

$           434,300.00

$      859,560.00

$ 1,073,000.00

J

Cost to date of previous year

$                            -  

$      434,300.00

$      859,560.00

K = I - J

Net Cost for the year

$           434,300.00

$      425,260.00

$      213,440.00

L = H - K

Gross Profits

$           258,000.00

$      138,240.00

$      140,760.00

----Answer---

.

Gross profit recognized in 2017

$ 258,000

Gross profit recognized in 2018

$ 138,240

Gross profit recognized in 2019

$ 140,760

---Under ‘this method’, Gross Profits are recognised ONLY when the contract is FULLY Complete.

Therefore, there will be no ‘gross profit’ for 2017 and 2018

---Working---

Contract Price

$       1,610,000.00

Total Cost

$       1,073,000.00

Gross Profits on Contract to be recorded in 2019

$           537,000.00

---Answers---

Gross profit recognized in 2017

$ 0

Gross profit recognized in 2018

$ 0

Gross profit recognized in 2019

$ 537,000

Accounts title

Debit

Credit

Construction in Progress [Req 1: Row ‘K’]

$ 425,260.00

Cash

$ 425,260.00

(construction cost incurred)

Accounts receivables [897000 – 301000]

$ 596,000.00

Billing on Construction contracts

$ 596,000.00

(amount billed during the year)

Cash [817000 – 271000]

$ 546,000.00

Accounts receivables

$ 546,000.00

(cash received)

Construction in Progress

$ 138,240.00

Construction expenses

$ 425,260.00

Construction Revenue

$ 563,500.00

(revenue recognised)

1) No profit or loss will be recorded in the year 2017 and 2018 under Compete Contract Method .

2) The Profits or loss under both methods will be Exactly same, The only difference is Profit or loss is recognised in year of completion in case of Completed Contract method and under Percentage on completion method Profit or loss is recognised in all years in which work is done.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote