Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data:
Recently, Job T629 was completed with the following characteristics:
The predetermined overhead rate is closest to:
Garrison 16e Rechecks 2017-08-01
Multiple Choice
$8.10 per machine-hour
$2.10 per machine-hour
$3.90 per machine-hour
$6.00 per machine-hour
Total machine-hours 80,000 Total fixed manufacturing overhead cost $ 312,000 Variable manufacturing overhead per machine-hour $ 2.10Explanation / Answer
Predetermined overhead rate = Estimated fixed overhead rate +estimated variable overhea rate
= [312000/80000] + 2.10
= 3.9+ 2.1
= $ 6 per MH
correct option is "D"
**Overhead rate= estimated overhead /estimated machine hours