In a large steel mill, prior to pouring the steel into a continuous casting mach
ID: 2074031 • Letter: I
Question
In a large steel mill, prior to pouring the steel into a continuous casting machine to produce slabs, the steel is deoxidized using aluminum. Al will react with dissolved oxygen in the molten steel to form solid Al20s particles which will rise to the top of the molten steel pool held in a ladle (the oxide can be skimmed off or become part of the slag before the steel is cast). In a particular 6. ladle. Assuming the weight % of aluminum added to the steel is 0.005% and the process needs to be completed in 30 seconds, calculate the speed (m/s) at which the aluminum wire must be fed into a 30-ton bath of steel in the ladle.Explanation / Answer
Density of aluminium = 2712 Kg/ m3
mass of Steel = 30000 Kg
mass of Al required = 0.005/100 * 30000
=1.5 Kg
Volume of Al required = mass / density
=1.5 / 2712 = 0.000553 m3
Area of cross Section = 3 * Pi * R2
=0.0002355 m2
Time = 30 s
Length = Volume / cross Section
=2.348 m
Speed = Length / time = 2.348/ 30 =0.0782 m/s
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.