During a company team building event, you had the opportunity to talk to a colle
ID: 1996672 • Letter: D
Question
During a company team building event, you had the opportunity to talk to a colleague project manager. She told you that in her current project, actual costs were 12% under the cumulated costs budgeted for today. What do you think of the situation? The information given to you by the colleague is not sufficient to assess the project performance The original cost forecasting and budgeting must have been poor to allow for such a variation None of these statements are valid An increase in costs during the rest of the project is likely to bring the costs back to the baseline level The project will probably be completed with the total costs remaining under budget until the endExplanation / Answer
since , for the current project ,actual cost were 12 % under the cumulated cost budgeted for that day.
this is a very less amount compared to total budget for that day.
so the coorect answer will be option 4 & 5.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.