"border: 0px; height: 0px; margin: 0px; padding: 0px; width: 707px">
A left-turn movement has a maximum arrival rate of 200
veh/h.
The saturation flow of this movement is 1400 veh/h. For this
approach, the yellow time is 4 seconds, all red time is 2
seconds
and total lost time is 3 seconds. The cycle lenght is 120
seconds.
What minimum displayed green time must be provided to ensure
to
ensure that the queue in each cycle clears, and what is the
total
delay per cycle and delay per vehicle for this green
time?(Assuming
D/D/1 queuing)
Explanation / Answer
ocw.korea.edu/ocw/college-of-engineering/transportation...
or....
http://ops.fhwa.dot.gov/publications/fhwahop08024/chapter3.htm this link might help you