Need help for that, what is the task type for task 0 and task 1 ??11:28 Haiyue@
ID: 1765878 • Letter: N
Question
Need help for that, what is the task type for task 0 and task 1 ??11:28 Haiyue@ The University of Sydney (Students) iPad? * 64%- ?? ?? ?? ?? B IU abe SAMPLE ENGG1850 Semester x, 20x Question 5-On Project Tool (MS Project) and Monitoring & Control 25 Marks] (a) The following detailed Gantt chart shows part of the plan for Ken's computer network system training project. Observe the chart carefully and answer the following questions as per Figure 2. 5 marks] Ken's Network Training Project 4.75 days 8hrs $2,800.00 75 days hrs Trainers 5 days hrs 5800.00 2.75 days . Figure 2 Detailed Gantt Chart (i) What type of task is task 0 and task 1? mark] (ii) What does the duration variance of 4.75 days mean? [I mark]Explanation / Answer
(i) The task number 0 is Kens network training project, the task number 1 is documentation
There are 3 types of task types in the gantt chart
Parent task
Normal task
milestone task
The task number 0 is kens network training project this type of task is a parent task since this includes all the remaining tasks and it is having a start time and end time
Task number 1 is documentation, this type of task is a normal task, since it does not involve any other tasks, and has a definite start time and end time
(ii) The duration variance is a parameter which is useful for measuring the progress of the project, for example a baseline is set for a project and after few days we want to review the status of the project, then the duration variance is useful, here it is 4.5 days, that means the project is going to take 4.5 days more than the scheduled duration.