1. Design-Build (25 points): a. (5) Explain the differences between a Design-Bui

ID: 1713540 • Letter: 1

Question

1. Design-Build (25 points): a. (5) Explain the differences between a Design-Build and a Design-Bid-Build contract. b. (5) Discuss the advantages/disadvantages of a Design-Build contract c. (5) Explain the ways that a design-bid product delivery team can be formed (who is the leading team member). LnsantDuine d. (5) What happens during Phase One and Phase Two of a two-phase sdetion proce d. phase oneal the best volue so rte curet, oe1n here 20 the nu naPhaseTwo ofatwo-hasese eetin rocess (5) What happens during Phu (5) Give three examples of selection criteria that an owner would use to select the winning Design-Build proposal. e.

Explanation / Answer

a) Design build: Under this method, an owner typically hires a single entity, the design/builder, to perform both design and construction under a single contract. Portions

or all of the design and construction may be performed by the entity or subcontracted to other companies. DB is characterized by high levels of collaboration between the design and construction disciplines, input from multiple trades into the design, and a single entity bearing project risk. Typically, the general contractor is responsible contractually for this delivery method.

Design-bid-build: Here the owner contracts separately with a designer and a contractor. The design firm is hired to deliver 100 percent complete

design documents. The owner or agent then solicits fixed price bids from contractors to perform the work. Designers and contractors bear no contractual obligationto one another and the owner bears all risk associated with the completeness of the design documents.

b) Advantages and Disadvantages of design build contract:

Advantages

disadvantages:

d) Phase one:

(1) The scope of work;

(2) The phase-one evaluation factors, including.

(i) Technical approach (but not detailed design or technical information)

(ii) Technical qualifications, such as.

(A) Specialized experience and technical competence;

(B) Capability to perform;

(C) Past performance of the offeror’s team

Phase two:

Phase Two of the solicitation shall require submission of technical and price proposals, which shall be evaluated separately.

Technical evaluation factors include design concepts, management approach, key personnel, and proposed technical solutions.

(a) The award decision is based on evaluation factors and significant subfactors that are tailored to the acquisition.

(b) Evaluation factors and significant subfactors must.

(1) Represent the key areas of importance and emphasis to be considered in the source selection decision.

(2) Support meaningful comparison and discrimination between and among competing proposals.