Susan, a project manager, uses a work breakdown structure to list the elemental
ID: 1713123 • Letter: S
Question
Susan, a project manager, uses a work breakdown structure to list the elemental tasks of a project. She then asks the team members responsible for each of these tasks to give her an estimate of the cost required to accomplish each task. Next, she adds indirect costs such as administrative costs and a reserve for contingencies to the total task cost and files her budget with the accounting department. In this scenario, Susan is using Oa. top-down budgeting O b.bottom-up budgeting ° c. Lateral budgeting d.agile project budgetingExplanation / Answer
It is bottom-up budgeting as you are starting with a plan of events to do, and then cost it up to get total budget.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.