b. Graphically documented RFI\'s c. Plans, Sections & Elevations d. Renderings w

ID: 1712534 • Letter: B

Question

b. Graphically documented RFI's c. Plans, Sections & Elevations d. Renderings with dimensions e. Perspectives & Isometrics Page Up 4. In concrete construction what is the difference between a control joint and a construction joint? age A control joint refers to a joint that is placed on amount of work completion in a day and a construction joint controls cracking. a. b. A control joint controls structural movement, whereas a constru c. d. e. prevents movement. Construction joints and Control joints are the same thing. Construction joints need sealed whereas control joints are left open. A control joint is used to control cracking, that is placed based on amount of work completion in a day. a construction joint refers to a joint 15. For the remote site below, which of the four locations indicated is most suitable for the development of a naturally fed fire-protection pond? Circle your answer.b a. Site A b. Site B C. Site C d. Site D e. Any of the sites would be suitable 16. In what phases of design would the design team draw something like what is illustrated below? a. Construction Administration/Commissioning b. Schematic Design/Design Development C. Programming/Predesign d. Technical drawings & specifications

Explanation / Answer

14) option "e" is correct .

control/contraction joints used to control random cracking in concrete. Construction joint kept at the end of days work to continue the work next day where multiple concrete placements.

15)option B is correct.

in the given map contours in Site B are decreasing inward, it is showing depression so depression area is suitable for pond.

16) option "d" is correct.

during design phase technical drawings and specifications are very important to proceed the work without any deviations to reach final outcome.