Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

5. The following lump sum cost categories will be incurred by a project: a. Dewa

ID: 1711843 • Letter: 5

Question

5. The following lump sum cost categories will be incurred by a project:

a. Dewatering due to rain

b. Stormwater management

c. Site security

d. Construction insurance

e. Tailgate safety meetings

The number of working days for the project were determined to be 90 days with 8 weather days scattered throughout the working days. Two national holidays will occur during this period.

Costs for the project are:

Dewatering costs are $368.56/hr for 6 hours per weather day

Stormwater Management is $1025/weather day

Site Security is $247.62/calendar day

Construction insurance is $14,500/month or portion of a month

Tailgate safety meeting occur each week or partial week that work occurs for 1 hour

Crew costs are $575.35/hr

What is the total lump sum cost (the sum of all of these costs) for these items?

Explanation / Answer

step1-

Dewatering costs are $368.56/hr for 6 hours per weather day

As per question 8 weather days scattered throughout the working days.

Therefore, Total Dewatering costs =368.56*6(for one day per 6 hours)

=368.56*6*8

=17690.88$

Step 2-

Stormwater Management is $1025/weather day.

As per question 8 weather days scattered throughout the working days

Therefore, total cost in Stormwater Management = 1025*8

=8200 $

Step 3-

Site Security is $247.62/calendar day

  calendar days: All days in a month, including weekends and holidays.

The number of working days for the project were determined to be 90 days.

Therefore, 247.62*90

=22285.8 $

Step 4-

Construction insurance is $14,500/month or portion of a month.

The number of working days for the project were determined to be 90 days.

Hence, 1 month has 30days

3 month has 90 days

Therefore, 14500*3

=43500$

Step 5-

Tailgate safety meeting occur each week or partial week that work occurs for 1 hour

Crew costs are $575.35/hr

As per question the number of working days for the project were determined to be 90 days.

Hence there are 15 weeks in 90 days

Therefore, 575.35*15

=8630.25$

So,

The total sum of above is the total lump sum cost (the sum of all of these costs) for these items

=17690.88+8200+22285.8+43500+8630.25

= 100,306.93$

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote