n the cut-and-fill method, ____.

rock bolts are fastened to stable bedrock

material is removed from the up a slope and placed at the base

material is removed from the base of a slope

benches are cut into a hillside

retaining walls are constructed and anchored into bedrock

a.

rock bolts are fastened to stable bedrock

b.

material is removed from the up a slope and placed at the base

c.

material is removed from the base of a slope

d.

benches are cut into a hillside

e.

retaining walls are constructed and anchored into bedrock

Explanation / Answer

b is the right answer , the amount of material is removed and filled after wards whihc doesnot matched to the previous height