Three different alternatives shown in table below are being considered by Kal Te

ID: 1241627 • Letter: T

Question

Three different alternatives shown in table below are being considered by Kal Tech Engineering

systems. Assume that alternatives X and Z are replaced at the end of their lives.

Data

Alternative X

Alternative Y

Alternative Z

Initial Cost

$6,000

$1,000

$1,500

Annual Benefits

$810

$125

$230

Useful Life in Years

20

Infinity

10

Interest

none

12%

none

The NPV of alternative

Data

Alternative X

Alternative Y

Alternative Z

Initial Cost

$6,000

$1,000

$1,500

Annual Benefits

$810

$125

$230

Useful Life in Years

20

Infinity

10

Interest

none

12%

none

Explanation / Answer

b. Alternative Y is the most desirable alternative.