Two storage structures, given code names Y and Z, are being considered for a mil

ID: 1221984 • Letter: T

Question

Two storage structures, given code names Y and Z, are being considered for a military base located in Sontaga. The military uses a 5 percent/year expected rate of return and a 24-year life for decisions of this type. The relevant char-acteristics for each structure are shown below.

a. What is the present worth of each machine?

b. What is the decision rule for determining the preferred machine based on present worth ranking?

c. Which structure should be recommended?

First Cost Estimated Life Estimated Salvage Value Annual Maintenance Cost Structure Y $4,500 12 years None $1,000 Structure Z $10,000 24 years $1,800 $720

Explanation / Answer

a) The present worth of structure Y

PW =- $ 4,500 - $ 1000/1.051 -   $ 1000/1.052 -   $ 1000/1.053 - $ 1000/1.054 - $ 1000/1.055 - $ 1000/1.056 - $ 1000/1.057 - $ 1000/1.058 - $ 1000/1.059 - $ 1000/1.0510 -   $ 1000/1.0511 - $ 1000/1.0512 - $ 1000/1.0513 - - $ 1000/1.0514 - $ 1000/1.0515 - $ 1000/1.0516 - $ 1000/1.0517 - $ 1000/1.0518 - $ 1000/1.0519 - $ 1000/1.0520 - - $ 1000/1.0521 - $ 1000/1.0522 - $ 1000/1.0523 - $ 1000/1.0524

PW of structure Y = -$ 18,299

Present worth of structure Z = -$ 10,000 - $ 720 /1.051 -   $ 720 /1.052 -   $ 720 /1.053 - $ 720 /1.054 - $ 720 /1.055 - $ 720 /1.056 - $ 720 /1.057 - $ 720 /1.058 - $ 720 /1.059 - $ 720 /1.0510 -   $ 720 /1.0511 - $ 720 /1.0512 - $ 720 /1.0513 - - $ 720 /1.0514 - $ 720 /1.0515 - $ 720 /1.0516 - $ 720 /1.0517 - $ 720 /1.0518 - $ 720 /1.0519 - $ 720 /1.0520 - - $ 720 /1.0521 - $ 720 /1.0522 - $ 720 /1.0523 +   $ 1,080 /1.0524  

PW of structure Z = -$ 19,377

=====================================================================================

b) The decision rule for determining the preferred machine based on present worth ranking is to select the machine with the lowest PW of the annual maintenance cost.

=================================================================================

C) The structure to be recommended is Y .

===================================================================================

Year                  Cash Flows Structure Y Structure Z 0 ($4,500) ($10,000) 1 ($1,000) ($720) 2 ($1,000) ($720) 3 ($1,000) ($720) 4 ($1,000) ($720) 5 ($1,000) ($720) 6 ($1,000) ($720) 7 ($1,000) ($720) 8 ($1,000) ($720) 9 ($1,000) ($720) 10 ($1,000) ($720) 11 ($1,000) ($720) 12 ($1,000) ($720) 13 ($1,000) ($720) 14 ($1,000) ($720) 15 ($1,000) ($720) 16 ($1,000) ($720) 17 ($1,000) ($720) 18 ($1,000) ($720) 19 ($1,000) ($720) 20 ($1,000) ($720) 21 ($1,000) ($720) 22 ($1,000) ($720) 23 ($1,000) ($720) 24 ($1,000) $1,080