Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem Set 8 Delta Corporation has the following capital structure: Cost (after

ID: 1169926 • Letter: P

Question

Problem Set 8

Delta Corporation has the following capital structure:

Cost (after tax)

Weights

Weighted Cost

Debt

9.1%

60%

Preferred stock

10.6%

5%

Common equity (retained earnings)

11.1%

35%

Weighted Average Cost of Capital

Calculate the weighted average cost of capital (WACC) and use it for the cost of capital interest rate for the rest of this problem. In other words, the WACC becomes the discount rate for the net present value calculations.

Assume Delta has three different (mutually exclusive) projects that are being considered. Listed below are the cash flows for the projects.

Project 1

Project 2

Project 3

Initial investment

$50,000

Initial Investment

$48,000

Initial Investment

$62,000

Cash Flow Year 1

$10,000

Cash Flow Year 1

$32,000

Cash Flow Year 1

$15,000

Cash Flow Year 2

$30,000

Cash Flow Year 2

$30,000

Cash Flow Year 2

$15,000

Cash Flow Year 3

$22,000

Cash Flow Year 3

0

Cash Flow Year 3

$15,000

Cash Flow Year 4

$8,000

Cash Flow Year 4

0

Cash Flow Year 4

$15,000

Cash Flow Year 5

$6,000

Cash Flow Year 5

0

Cash Flow Year 5

$2,000

For each of the projects shown above, calculate the Payback Period, Internal Rate of Return (IRR), and Net Present Value (NPV). Make a table in APA format and label it Table 1. In this table show the three projects and the values for payback period, IRR, and NPV. Write a one paragraph explanation of which projects Delta management should choose and why. Explain whether the different calculation methods give you different results on which project(s) should be chosen and why.

*List for years 0-5 for the payback period, IRR and the NPV, Label each clearly.

Cost (after tax)

Weights

Weighted Cost

Debt

9.1%

60%

Preferred stock

10.6%

5%

Common equity (retained earnings)

11.1%

35%

Weighted Average Cost of Capital

Explanation / Answer

Weights

Weighted Cost

Cost (after tax)

Debt

9.10%

60%

5.4600%

Preferred stock

10.60%

5%

0.5300%

Common equity (retained earnings)

11.10%

35%

3.8850%

Weighted Average Cost of Capital

Sum of weight*cost

9.8750%

Project 1

Project 2

Project 3

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 9.88%

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 9.88%

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 9.88%

0

($50,000)

($50,000)

0

($48,000)

($48,000)

0

($62,000)

($62,000)

1

$10,000

$9,100.84

1

$32,000

$29,122.68

1

$15,000

$13,651.26

2

$30,000

$24,847.57

2

$30,000

$24,847.57

2

$15,000

$12,423.79

3

$22,000

$16,583.14

3

$0

$0.00

3

$15,000

$11,306.69

4

$8,000

$5,488.02

4

$0

$0.00

4

$15,000

$10,290.03

5

$6,000

$3,745.92

5

$0

$0.00

5

$2,000

$1,248.64

NPV

sum of present value of cash flow

$9,765

NPV

sum of present value of cash flow

$5,970

NPV

sum of present value of cash flow

($13,080)

IRR

Using IRR function in MS excel =irr(-50000,10000,30000,22000,8000,6000)

18.15%

IRR

Using IRR function in MS excel =irr(-48000,32000,30000,0,0,0)

19.13%

IRR

Using IRR function in MS excel =irr(-62000,15000,15000,15000,15000,15000)

0%

Payback period

Payback period

Payback period

Project 1

Project 2

Project 3

Year

cash flow

cumulative cash flow

Year

cash flow

cumulative cash flow

Year

cash flow

cumulative cash flow

0

($50,000)

0

($48,000)

0

($62,000)

1

$10,000

$10,000

1

$32,000

$32,000

1

$15,000

$15,000

2

$30,000

$40,000

2

$30,000

$18,000

Amount to be recovered

2

$15,000

$30,000

Amount to be recovered

3

$22,000

10000

Amount to be recovered

3

$0

3

$15,000

$45,000

4

$8,000

4

$0

4

$15,000

$60,000

5

$6,000

5

$0

5

$2,000

$62,000

payback period

year before the final recovery+(amount to be recovered/cash flow of final year of recovery

2+(10000/22000)

2.45

payback period

year before the final recovery+(amount to be recovered/cash flow of final year of recovery

1+(18000/30000)

1.6

payback period

Entire amount is recovered in year 5 so Payback period is 5 years

Project

1

2

3

NPV

$9,765

$5,970

($13,080)

Project 1

IRR

18.15%

19.13%

0%

Project 2

Payback period

2.45

1.6

5

Project 2

As per different techniques of capital budgeting NPV suggest that Project 1 should be selected while IRR and PB period suggest Project 2 should be selected so in this situation conflict arise so it is better that Project 1 should be consided for selection as it is the best technique of capital budgeting because IRR takes an assumption of reinvestment of cash flow with the same rate equal to irr which in actual world is not possible and payback period ignores the time value of money so in case of mutual exclusive project project 1 should be selected.

Weights

Weighted Cost

Cost (after tax)

Debt

9.10%

60%

5.4600%

Preferred stock

10.60%

5%

0.5300%

Common equity (retained earnings)

11.10%

35%

3.8850%

Weighted Average Cost of Capital

Sum of weight*cost

9.8750%

Project 1

Project 2

Project 3

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 9.88%

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 9.88%

Year

cash flow

present value of cash flow = cash flow/(1+r)^n r= 9.88%

0

($50,000)

($50,000)

0

($48,000)

($48,000)

0

($62,000)

($62,000)

1

$10,000

$9,100.84

1

$32,000

$29,122.68

1

$15,000

$13,651.26

2

$30,000

$24,847.57

2

$30,000

$24,847.57

2

$15,000

$12,423.79

3

$22,000

$16,583.14

3

$0

$0.00

3

$15,000

$11,306.69

4

$8,000

$5,488.02

4

$0

$0.00

4

$15,000

$10,290.03

5

$6,000

$3,745.92

5

$0

$0.00

5

$2,000

$1,248.64

NPV

sum of present value of cash flow

$9,765

NPV

sum of present value of cash flow

$5,970

NPV

sum of present value of cash flow

($13,080)

IRR

Using IRR function in MS excel =irr(-50000,10000,30000,22000,8000,6000)

18.15%

IRR

Using IRR function in MS excel =irr(-48000,32000,30000,0,0,0)

19.13%

IRR

Using IRR function in MS excel =irr(-62000,15000,15000,15000,15000,15000)

0%

Payback period

Payback period

Payback period

Project 1

Project 2

Project 3

Year

cash flow

cumulative cash flow

Year

cash flow

cumulative cash flow

Year

cash flow

cumulative cash flow

0

($50,000)

0

($48,000)

0

($62,000)

1

$10,000

$10,000

1

$32,000

$32,000

1

$15,000

$15,000

2

$30,000

$40,000

2

$30,000

$18,000

Amount to be recovered

2

$15,000

$30,000

Amount to be recovered

3

$22,000

10000

Amount to be recovered

3

$0

3

$15,000

$45,000

4

$8,000

4

$0

4

$15,000

$60,000

5

$6,000

5

$0

5

$2,000

$62,000

payback period

year before the final recovery+(amount to be recovered/cash flow of final year of recovery

2+(10000/22000)

2.45

payback period

year before the final recovery+(amount to be recovered/cash flow of final year of recovery

1+(18000/30000)

1.6

payback period

Entire amount is recovered in year 5 so Payback period is 5 years

Project

1

2

3

NPV

$9,765

$5,970

($13,080)

Project 1

IRR

18.15%

19.13%

0%

Project 2

Payback period

2.45

1.6

5

Project 2

As per different techniques of capital budgeting NPV suggest that Project 1 should be selected while IRR and PB period suggest Project 2 should be selected so in this situation conflict arise so it is better that Project 1 should be consided for selection as it is the best technique of capital budgeting because IRR takes an assumption of reinvestment of cash flow with the same rate equal to irr which in actual world is not possible and payback period ignores the time value of money so in case of mutual exclusive project project 1 should be selected.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote