Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

ooo Verizon LTE 7:03 PM * 47% Homework 5 Homework 5.docx AREC/ECON 346- Homework

ID: 1121652 • Letter: O

Question

ooo Verizon LTE 7:03 PM * 47% Homework 5 Homework 5.docx AREC/ECON 346- Homework 5 Due: Wednesday December 6, 11:59pmm Below is a table showing the annual benefits and costs for two recreation projects. Project A, which has a larger up-front cost, will increase the capacity of the recreation area allowing for increasing numbers of users over 10 years Project B will maintain the area to accommodate the current use levels onl 00 7502,000 750 2 3509502 17S 750 75 750 75 750 6 3501,750 175 750 75 750 75 750 93502.350 9 175 750 10 350 2.55010 175 750 4 350,3504 5 350 ,5505 8 350 2,1508 1.(12 points) Calculate the Net Preset Value of each project using a 4% discount rate Use the spreadsheet attached to the assignment to do your calculations and submit it along with answers to the question below 2. (6 points) Based on the net present value, which project 3. (6 points) If you were only looking at the B/C ratio which 4. (12 points) Calculate the Net Present Value of each project 5. (6 points) Does your preferred project change with the higher 6. (8 points) Explain what is going on when the discount rate is The formula for present value is: would you choose? would you choose? using a 10% discount rate discount rate? increased. Courses Calendar To Do Notifications Messages

Explanation / Answer

Answer:

1. Net present value is calculated below by using the formula:

PV at 4% = 1/(1+4%)t where t is year and

PV of net cash flow = PV at 4% * cash flow

net cash = benefit-cost

Net present vaalue = summation of PV of net cash

Project A

Year

Costs

Benefits

Net cash

PV at 4%

PV of net cash

1

6500

750

-5750

0.961538

-5528.846154

2

350

950

600

0.924556

554.7337278

3

350

1150

800

0.888996

711.1970869

4

350

1350

1000

0.854804

854.804191

5

350

1550

1200

0.821927

986.3125281

6

350

1750

1400

0.790315

1106.440336

7

350

1950

1600

0.759918

1215.868501

8

350

2150

1800

0.73069

1315.242369

9

350

2350

2000

0.702587

1405.173471

10

350

2550

2200

0.675564

1486.241171

NPV

4107.167229

Project B

Year

Costs

Benefits

Net cash

PV at 4%

PV of net cash

1

2000

750

-1250

0.961538

-1201.923077

2

175

750

575

0.924556

531.6198225

3

175

750

575

0.888996

511.1729062

4

175

750

575

0.854804

491.5124098

5

175

750

575

0.821927

472.6080864

6

175

750

575

0.790315

454.4308523

7

175

750

575

0.759918

436.9527426

8

175

750

575

0.73069

420.1468679

9

175

750

575

0.702587

403.987373

10

175

750

575

0.675564

388.4493971

NPV

2908.957381

2) Projecthaving greater NPV should be choosen. As project A has greater NPV than NPV of B then project A should be choosen.

3) B/C ration can be calculated by dividing all benefits to all cash as follows:

B/C ratio of B = 3575/7500 = 2.097

and B/C ratio of A = 16500/9650 = 1.70

As B/C ratio of B is greater than A then B should have been selected.

4) Using 10% discount rate:

Project A

Year

Costs

Benefits

Net cash

PV at 10%

PV of net cash

1

6500

750

-5750

0.909091

-5227.272727

2

350

950

600

0.826446

495.8677686

3

350

1150

800

0.751315

601.0518407

4

350

1350

1000

0.683013

683.0134554

5

350

1550

1200

0.620921

745.1055877

6

350

1750

1400

0.564474

790.2635021

7

350

1950

1600

0.513158

821.0529892

8

350

2150

1800

0.466507

839.7132844

9

350

2350

2000

0.424098

848.1952367

10

350

2550

2200

0.385543

848.1952367

NPV

1445.186174

Project B

Year

Costs

Benefits

Net cash

PV at 10%

PV of net cash

1

2000

750

-1250

0.909091

-1136.363636

2

175

750

575

0.826446

475.2066116

3

175

750

575

0.751315

432.0060105

4

175

750

575

0.683013

392.7327368

5

175

750

575

0.620921

357.0297608

6

175

750

575

0.564474

324.5725098

7

175

750

575

0.513158

295.065918

8

175

750

575

0.466507

268.2417436

9

175

750

575

0.424098

243.8561306

10

175

750

575

0.385543

221.6873914

NPV

1874.035177

Project A

Year

Costs

Benefits

Net cash

PV at 4%

PV of net cash

1

6500

750

-5750

0.961538

-5528.846154

2

350

950

600

0.924556

554.7337278

3

350

1150

800

0.888996

711.1970869

4

350

1350

1000

0.854804

854.804191

5

350

1550

1200

0.821927

986.3125281

6

350

1750

1400

0.790315

1106.440336

7

350

1950

1600

0.759918

1215.868501

8

350

2150

1800

0.73069

1315.242369

9

350

2350

2000

0.702587

1405.173471

10

350

2550

2200

0.675564

1486.241171

NPV

4107.167229