Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1.A company is considering the following projects: Project A B C Construction co

ID: 1115656 • Letter: 1

Question

1.A company is considering the following projects:

Project

A

B

C

Construction cost 1000$

100

150

300

Annual Benefits 1000$/yr (prob)

30(0.2) 40(0.6) 45(0.2)

25(0.3) 35(0.6) 40(0.1)

45(0.1) 45(0.6) 50(0.3)

Life yrs

7

8

9

Their minimum acceptable B/C is 3.0. Which project should they select, if any at all? The rate is 4%. Clue: Select the project that maximizes the probability of B/C>3.

Project

A

B

C

Construction cost 1000$

100

150

300

Annual Benefits 1000$/yr (prob)

30(0.2) 40(0.6) 45(0.2)

25(0.3) 35(0.6) 40(0.1)

45(0.1) 45(0.6) 50(0.3)

Life yrs

7

8

9

Explanation / Answer

B/C is the ratio of sum of present value of all the benefits with present value of all costs

Present value = cash flow/(1+r)n, where r is rate of return and n is number of years

r = 4%

For project A, Construction cost = $100

Annual Benefit = $30 with probability of 0.2

Annual Benefit = $40 with probability of 0.6

Annual Benefit = $45 with probability of 0.2

Life = 7 years

If annual benefit is 30 then PV of benefit = 30/(1+0.04)1 + 30/(1.04)2 + ................................. + 30/(1.04)7 = 180.06

B/C = 180.06/100 = 1.80

If annual benefit is 40 then PV of benefit = 40/(1+0.04)1 + 40/(1.04)2 + ................................. + 40/(1.04)7 = 240.08

B/C = 240.08/100 = 2.40

If annual benefit is 45 then PV of benefit = 45/(1+0.04)1 + 45/(1.04)2 + ................................. + 45/(1.04)7 = 270.09

B/C = 270.09/100 = 2.70

B/C ratio for project A = 0.2*1.80 + 0.6*2.40 + 0.2*2.70 = 2.34

For project B, Construction cost = $150

Annual Benefit = $25 with probability of 0.3

Annual Benefit = $35 with probability of 0.6

Annual Benefit = $40 with probability of 0.1

Life = 8 years

If annual benefit is 25 then PV of benefit = 25/(1+0.04)1 + 25/(1.04)2 + ................................. + 25/(1.04)8 = 168.32

B/C = 168.32/150 = 1.12

If annual benefit is 35 then PV of benefit = 35/(1+0.04)1 + 35/(1.04)2 + ................................. + 35/(1.04)8 = 235.65

B/C = 235.65/150 = 1.57

If annual benefit is 40 then PV of benefit = 40/(1+0.04)1 + 40/(1.04)2 + ................................. + 40/(1.04)8 = 250.22

B/C = 250.22/150 = 1.67

B/C ratio for project B = 0.3*1.12 + 0.6*1.57 + 0.1*1.67 = 1.45

For project C, Construction cost = $300

Annual Benefit = $45 with probability of 0.1

Annual Benefit = $45 with probability of 0.6

Annual Benefit = $50 with probability of 0.3

Life = 9 years

If annual benefit is 45 then PV of benefit = 45/(1+0.04)1 + 45/(1.04)2 + ................................. + 45/(1.04)9 = 334.59

B/C = 334.59/300 = 1.12

If annual benefit is 50 then PV of benefit = 50/(1+0.04)1 + 50/(1.04)2 + ................................. + 50/(1.04)9 = 371.77

B/C = 371.77/300 = 2.48

B/C ratio for project B = 0.1*1.12 + 0.6*1.12 + 0.3*2.48 = 1.52

B/C for every project is less than 3 so no project shoul be selected