A municipal power plant uses natural gas from an existing pipeline at an annual
ID: 1110387 • Letter: A
Question
A municipal power plant uses natural gas from an existing pipeline at an annual cost of $10,000 per year. A new pipeline would initially cost $35,000, but it would reduce he annual cost to S4 000 per year. Assume an analysis period of 20 years and no salvage value for either pipeline. The interest rate is 7%. Using the equivalent uniform annual cost (EUAC) should the new pipeline be built? Hint: If the EUAC is less than the annual cost of the existing pipeline, then the new pipeline should be constructed) O a. The new pipeline should not be constructed b. The new pipeline should be constructedExplanation / Answer
Initial cost of new pipeline = $35,000
Annual cost of new pipeline = $4,000
Time period = 20 years
Interest rate = 7%
Calculate the Equivalent Uniform Annual Cost (EUAC) of new pipeline -
EUAC = $35,000(A/P, 7%, 20) + $4,000
EUAC = ($35,000 * 0.0944) + $4,000
EUAC = $3,304 + $4,000
EUAC = $7,304
The EUAC of new pipeline is $7,304
The EUAC of new pipeline is less than the annual cost of exisiting pipeline.
So, it is beneficial and cost saving to construct the new pipeline.
Thus, the new pipeline should be constructed.
Hence, the correct answer is the option (b).
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.