the owner of a downtown parking lot has employed a civil engineering consulting

ID: 1099856 • Letter: T

Question

the owner of a downtown parking lot has employed a civil engineering consulting frim to advise him on the economic feasibility of constructing an office building on the site. bill samuels, a newly hired civil engineer, has been assigned to make the analysis. he has assembled the following data

alternative                  total investment              total net annual revenue
sell parking lot                   0                                 0
keep parking lot 200,000    22,000
build 1 story building        400,000    60,000
build 2 story building        555,000    72,000
build 3 story building         750,000                    100,000
build 4 story building         875,500                    105,000
build 5 story building         1,000,000 120,000

the analysis period is be 15 years. for all alternatives, the property has an estimated resale(salvage) value at the end of 15 years equal to the present total investement.
(a) constuct a choice table for interest rate from 0% to 100%
(b)if the MARRR is 10%, what recommendation should bill make?

Explanation / Answer

This problem is one of neither fixed input nor fixed output. When the estimated resale value equals the present total investment we have the special case where: A = Pi or i = A/P

NPV = 0 = (-P) + (P/A) + (P/F=P)

Reduces to simple interest of i = A/P

Alternative

P*

A*

i

P

A

i

Decision

Sell Parking Lot

0

0

0%

Keep Parking Lot

$200

$22

11%

$200

$22

11%

Keep Lot

Build 1 story building

$400

$60

15%

$200

$38

19%

1 story

Build 2 story

$555

$72

12.9%

$155

$12

7.7%

1 story

Build 3 story

$750

$100

13.3%

$350

$40

11.4%

3 story

Build 4 story

$875

$105

12%

$125

$5

4.0%

3 story

Build 5 story

$1,000

$120

12%

$250

$20

8.0%

3 story

Ans: Choose 3-story

Alternative

P*

A*

i

P

A

i

Decision

Sell Parking Lot

0

0

0%

Keep Parking Lot

$200

$22

11%

$200

$22

11%

Keep Lot

Build 1 story building

$400

$60

15%

$200

$38

19%

1 story

Build 2 story

$555

$72

12.9%

$155

$12

7.7%

1 story

Build 3 story

$750

$100

13.3%

$350

$40

11.4%

3 story

Build 4 story

$875

$105

12%

$125

$5

4.0%

3 story

Build 5 story

$1,000

$120

12%

$250

$20

8.0%

3 story