A county in Tennessee is considering the following public interest project. Init

ID: 1098306 • Letter: A

Question

  1. A county in Tennessee is considering the following public interest project.
    Initial Cost $22.5M Annual Maintenance Cost $525K EUAB $3.3M
    Given a useful life of 12 years and an interest rate of 4%, the benefit /cost ratio is _____________________. A. 1.01 B. 1.67 C. 1.48 D. 1.51.
A county in Tennessee is considering the following public interest project.
Initial Cost $22.5M Annual Maintenance Cost $525K EUAB $3.3M
Given a useful life of 12 years and an interest rate of 4%, the benefit /cost ratio is _____________________. A. 1.01 B. 1.67 C. 1.48 D. 1.51. A county in Tennessee is considering the following public interest project.
Initial Cost $22.5M Annual Maintenance Cost $525K EUAB $3.3M
Given a useful life of 12 years and an interest rate of 4%, the benefit /cost ratio is _____________________.
Given a useful life of 12 years and an interest rate of 4%, the benefit /cost ratio is _____________________. 1.01 1.67 1.48 1.51. Initial Cost $22.5M Annual Maintenance Cost $525K EUAB $3.3M

Explanation / Answer

b