Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Given two alternatives: Data A B First Cost $4,000 $6,000 Annual Cost $1,000 $50

ID: 1091678 • Letter: G

Question

Given two alternatives:

Data

A

B

First Cost

$4,000

$6,000

Annual Cost

$1,000

$500

Annual Benefit

$2,000

$2,200

Life, Years

4

10

Salvage Value

$3,000

$1,000

Assuming hat alternatives are replaced at the end of their useful life, determine the better alternative using annual cash flow analysis at an interest rate of 10%.

Alternative A, $786

Alternative B, $786

Alternative A, $384

Alternative B, $384

Data

A

B

First Cost

$4,000

$6,000

Annual Cost

$1,000

$500

Annual Benefit

$2,000

$2,200

Life, Years

4

10

Salvage Value

$3,000

$1,000

Explanation / Answer

First find Annual Net Present Value of both projects.

Both projects have same format, initial cost + annual cash flow (benefit - cost) + salvage value (at last year of project). Salvage value of Project a at year 4, salvage value for b at year 10.

NPV Project A = -4,000 + (2,000 - 1,000) * [(1+0.10)^4-1] / [0.10 (1+0.10)^4] + 3,000 / (1+0.10)^4

NPV Project A = -4,000 + 3,169.87 + 2,049.04

NPV Project A = $1,218.91

NPV Project B = -6,000 + (2,200 - 500) * [(1+0.10)^10-1] / [0.10 (1+0.10)^10] + 1,000 / (1+0.10)^10

NPV Project B = -6,000 + 10,445.76 + 385.54

NPV Project B = $4,831.30

Now NPV is calculates, using those NPV's as PV, find the yearly annuity for Annual cash flow of each project.

PV = A [(1+r)^n-1] / [r (1+r)^n]

Project A: 1,218.91 = EACF [(1+0.10)^4-1] / [0.10 (1+0.10)^4]

EACF Project A = 384.53

Project B: 4,831.30 = EACF [(1+0.10)^10-1] / [0.10 (1+0.10)^10]

EACF Project B = 786.27

EACF = Equivalent Annual Cash Flow

B. Alternative B, $786.................(answer)

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote